Question 1
Select the three statements that are true about the Project management Plan.
  1. It is created in the Manage Project Execution and Control phase.
  2. It is the single most important work product produced by the project manager.
  3. Its main focus is on scheduling the project.
  4. It is created by the project manager and the client.
  5. It is a conceptual work product comprised of process components detailing the tools and/or approach for each OUM Manage process.
  6. It provides a framework for the Analysis and Design processes.
Correct answer: BDF
Explanation:
* In OUM Manage, one of the first activities that occur during the Project Startup phase involves the Project Manager and the client (Project Sponsor) jointly creating the Project Management Framework.  This framework establishes the ground rules for the project and is the first step in communicating, establishing trust, and setting expectations. The key focus for the remainder of the Project Startup Phase is to evolve the Project Management Framework into a detailed Project Management Plan based on the agreed upon foundation.    * The project manager creates the project management plan following input from the project team and key stakeholders. The plan should be agreed and approved by at least the project team and its key stakeholders. Incorrect:Not A: Project Execution and Control runs concurrently with the Implement focus area phases. The purpose of the Project Execution and Control Phase is to provide adequate visibility into actual progress so that management can take effective actions when the project’s performance deviates significantly from the project plans. The Project Execution and Control Phase includes tracking and reviewing the projects accomplishments and results against documented WBS, project estimates, time schedule, resources plan, and cost budget, and adjusting these plans based on the actual accomplishment and results.
* In OUM Manage, one of the first activities that occur during the Project Startup phase involves the Project Manager and the client (Project Sponsor) jointly creating the Project Management Framework.  This framework establishes the ground rules for the project and is the first step in communicating, establishing trust, and setting expectations. 
The key focus for the remainder of the Project Startup Phase is to evolve the Project Management Framework into a detailed Project Management Plan based on the agreed upon foundation.    
* The project manager creates the project management plan following input from the project team and key stakeholders. The plan should be agreed and approved by at least the project team and its key stakeholders. 
Incorrect:
Not A: Project Execution and Control runs concurrently with the Implement focus area phases. The purpose of the Project Execution and Control Phase is to provide adequate visibility into actual progress so that management can take effective actions when the project’s performance deviates significantly from the project plans. The Project Execution and Control Phase includes tracking and reviewing the projects accomplishments and results against documented WBS, project estimates, time schedule, resources plan, and cost budget, and adjusting these plans based on the actual accomplishment and results.
Question 2
Select the three constraints that are missing in this Triple Constraint triangle.
  1. Usability
  2. Scope
  3. Cost
  4. Complexity
  5. Product
  6. Schedule
Correct answer: BCF
Explanation:
* Scope, Time & Cost together are termed as the Triple Constraints of a Project. * Risk avoidance involves changing the project plan to eliminate the risk or to protect the project objectives (time, cost, scope, quality) from its impact. The team might achieve this by changing scope, adding time, or adding resources (thus relaxing the so-called “triple constraint”) Note:
* Scope, Time & Cost together are termed as the Triple Constraints of a Project. 
* Risk avoidance involves changing the project plan to eliminate the risk or to protect the project objectives (time, cost, scope, quality) from its impact. The team might achieve this by changing scope, adding time, or adding resources (thus relaxing the so-called “triple constraint”) 
Note:
Question 3
Which two statements are true about the Change Control Board (CCB)?
  1. It meets daily during Project Execution and Control.
  2. It is an internal project organization that is responsible for reviewing and resolving change requests.
  3. It is a person, group, or business that has a shared interest in a particular set of activities.
  4. It escalates changes affecting scope to the steering committee.
Correct answer: BD
Explanation:
B: CCB is a review committee that discusses and approves requests for changes to On Demand customer system configurations. The change requests are fulfilled in the following ways:A work guideline is generated by engineering for operations to use and implement. The changes are included in Oracle Certified Configurations. D: A Steering Committee is a group of high-level stakeholders who are responsible for providing guidance on overall strategic direction. They do not take the place of a Sponsor, but help to spread the strategic input and buy-in to a larger portion of the organization. The Steering Committee is usually made up of organizational peers and is a combination of direct clients and indirect stakeholders. Some members on the Steering Committee may also sit on the Change Control Board.
B: CCB is a review committee that discusses and approves requests for changes to On Demand customer system configurations. The change requests are fulfilled in the following ways:
A work guideline is generated by engineering for operations to use and implement. 
The changes are included in Oracle Certified Configurations. 
D: A Steering Committee is a group of high-level stakeholders who are responsible for providing guidance on overall strategic direction. They do not take the place of a Sponsor, but help to spread the strategic input and buy-in to a larger portion of the organization. The Steering Committee is usually made up of organizational peers and is a combination of direct clients and indirect stakeholders. Some members on the Steering Committee may also sit on the Change Control Board.
Question 4
Which identifies the quality standards that are relevant to the project and how to satisfy them?
  1. Quality Assurance
  2. Quality Control
  3. Quality Planning
  4. Process Improvement
Correct answer: AD
Question 5
Select two objectives of the OUM Implement Elaboration phase.
  1. Confirm the project scope.
  2. Identify and validate the architecturally significant requirements.
  3. Identify key configuration decisions.
  4. Prepare the system for acceptance test and deployment.
  5. Address critical operational issues.
  6. Obtain acceptance.
Correct answer: BC
Explanation:
The goal of the Elaboration phase is to develop the detailed requirements, partition the solution, create any necessary prototypes, and baseline the architecture of the system. This effort results in a stable basis for the design and implementation effort in the Construction phase. The architecture evolves from the most significant requirements (B), those that have the greatest impact on the architecture of the system, and an assessment of risk. The stability of the architecture is evaluated through one or more architectural prototypes. During the Elaboration phase, the project team’s understanding of the client’s business requirements is verified to reduce development risk. Note:OUM includes the following phases. Inception  Elaboration  Construction  Transition  Production  Reference: OracleUnified Method (OUM) Oracle’s Full Lifecycle Method for Deploying Oracle-Based Business Solutions
The goal of the Elaboration phase is to develop the detailed requirements, partition the solution, create any necessary prototypes, and baseline the architecture of the system. This effort results in a stable basis for the design and implementation effort in the Construction phase. The architecture evolves from the most significant requirements (B), those that have the greatest impact on the architecture of the system, and an assessment of risk. The stability of the architecture is evaluated through one or more architectural prototypes. During the Elaboration phase, the project team’s understanding of the client’s business requirements is verified to reduce development risk. 
Note:
OUM includes the following phases. 
Inception  Elaboration  Construction  Transition  Production  
Reference: OracleUnified Method (OUM) Oracle’s Full Lifecycle Method for Deploying Oracle-Based Business Solutions
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX FILES

Use ProfExam Simulator to open VCEX files
ProfExam Screen

ProfExam
ProfExam at a 20% markdown

You have the opportunity to purchase ProfExam at a 20% reduced price

Get Now!